From zero to an approved workstation

Order of operations, decision authority per step, and the two thresholds where mistakes get expensive.

Area
TEMPEST/RÖS

How it is built

Eleven steps. The two expensive thresholds are the environment assessment and the installation approval.Before procurementProcurementInstallation and operationEnvironment assessmentLevel decisionSpecificationAwardInstallationInstallation approvalthreshold 1threshold 2
Eleven steps. The two expensive thresholds are the environment assessment and the installation approval.Before procurementProcurementInstallation and operationEnvironment assessmentLevel decisionSpecificationAwardInstallationInstallation approvalthreshold 1threshold 2
Eleven steps. The two expensive thresholds are the environment assessment and the installation approval.

How it works

Eleven steps from an empty room to an approved workstation. The order matters more than the speed, and two thresholds are where mistakes get expensive.

Threshold one: the environment assessment

The level follows the environment, not the classification of the information. Getting the assessment wrong sets every subsequent requirement wrong, and it is the cheapest thing on this list to redo and the most expensive to discover late.

Threshold two: the installation approval

Delivery is not acceptance. The installation is approved, not the equipment, and the payment plan should follow that. An installation that turns out to need a filter, a re-route or a different containment after acceptance is the single most common cost overrun in this field.

Hands soldering a circuit board under a work lamp

Next step

Designing something that is not here?

Send us the constraints. We build from idea to certified end product, and most of what is in the catalogue started that way.